November 5, 2026
In 1990, Carter Jackson asked his four daughters to agree to a conservation easement on the family ranch south of Glenwood Springs, so the land could never be developed commercially. According to The Sopris Sun, his daughter Sandy Jackson told City Council this June that her father counted the easement among the things he was proudest of. The land has stayed open ever since, a green buffer between the river and Highway 82.
That same stretch of pasture is where Glenwood Springs plans to land the eastern end of the South Bridge. The city has worked toward this second river crossing for years. Before it can build, it has to acquire about two acres of the Jackson Ranch, and the Aspen Valley Land Trust holds an easement on that land that prohibits development.
For anyone looking at homes on the south side of town, this is the useful thing to know. The bridge and the protected land beside it are tied up in the same unresolved process. Until that process ends, neither one is a fixed feature of the neighborhood.
The city's April 2025 project update traces the route. It starts at the Four Mile Road and South Midland Avenue roundabout, runs east along Airport Road, crosses the Roaring Fork River and ends at Highway 82. The update lists access connections for Holy Cross Energy, the Jackson Ranch, County Road 163 and Sky Ranch Drive.
On the way, the bridge crosses the river, the Roaring Fork Transportation Authority corridor and the Jackson Ranch. City officials have long called it a public safety and mobility improvement that would give south Glenwood Springs a second route out, as the Post Independent reported in June.
The money has been building for a while. In the April 2025 update, the city said the U.S. Department of Transportation awarded a $49.68 million grant on December 12, 2023. The city had also received $6 million in RFTA grants and congressional earmarks, and it put the total cost at an estimated $85 million. By June 2026, council coverage in The Sopris Sun was giving the estimate as about $80 million.
In mid-June, the project ran into two separate legal problems within a few days of each other.
The first came from Garfield County. In a June 16, 2026 release, the county said it would ask the district court to decide whether the bridge needs county 1041 review. It also asked the court to block construction on unincorporated county land until that question is answered. The county said the city's Location and Extent application, submitted June 2, was incomplete. The Sopris Sun noted that a 1041 review means public hearings before both the county Planning Commission and the Board of County Commissioners, which would add substantial time.
The second question was the land. On June 18, City Council voted 4-3 to acquire the property interests the project needs, using eminent domain if negotiations fail. Mayor Marco Dehm, Mayor Pro Tem Erin Zalinski and Councilors Mitchell Weimer and Sumner Schachter voted in favor. Councilors David Townsley, Ray Schmahl and Steve Smith voted against. The Post Independent reported that the remaining property issues involve Holy Cross Energy land, the Jackson property and the Aspen Valley Land Trust easement across it.
Holy Cross appeared open to selling. The Jackson parcel is different. City Attorney Karl Hanlon advised council that the city would have to go to court and use its condemnation powers to acquire it, The Sopris Sun reported. AVLT Deputy Director Torrey Udall told council the project runs against the easement's purposes, including protecting wetlands and wildlife habitat. In a June 17 letter, the land trust said the city's $545,100 appraisal was "well below" what the land would be worth with the easement removed.
The appraisal is not the final price, either. According to the Post Independent, Hanlon said the Jackson property's underlying zoning is commercial despite the easement, and both the city's and the Jackson family's appraisal teams valued the land based on that zoning. Udall warned that condemnation could cost the city more than expected, including damages beyond fair market value for harm to scenic, aesthetic, ecological and conservation values.
Council was clearly divided, but the majority framed the June vote as a way to reach a decision. Councilor Schachter said proceeding would "give us the full picture of whether we should proceed, or not" once construction bids came in during the fall. Mayor Dehm put it more directly, as quoted in The Sopris Sun:
"I'm sorry this is where we are. But we have to build this bridge for numerous reasons, and to kill it now would be foolish. We have to get to bid so we know where we're at."
The three councilors who voted no argued it was too early to acquire land the city might never use if the project were dropped.
Bids did not arrive in the fall. Notes from the city's September 1, 2026 Transportation Commission meeting, filed with the October 6 agenda, say the project will "likely" go to bid at the beginning of the year. The notes list two conditions for that. The city needs county permits before it can bid, and its right-of-way clearance is conditional because it "can't build anything on property that the City doesn't own." The same notes said a federal grant would be awarded "in the next day or two."
Set that next to the original timeline. The city's 2025 update said the federal grant required groundbreaking by September 2026. A January 2024 Post Independent report described an 18-month encumbrance deadline after the grant was signed, which the city then expected to fall around September 2026. That month has now passed, and the city's latest schedule has bidding in early 2027.
| Project issue or step | Latest public record | Date |
|---|---|---|
| County permits issued | Required before the city can bid | Sept. 1, 2026 commission notes |
| 1041 review | County lawsuit and injunction request filed | June 16, 2026 |
| Jackson Ranch strip acquired | Council authorized eminent domain, 4-3 | June 18, 2026 |
| Holy Cross Energy land acquired | Utility appeared open to a sale | June 2026 coverage |
| Construction bid | "Likely" at the beginning of 2027 | Sept. 1, 2026 commission notes |
The city needs county permits before it can bid, and it needs to acquire the Jackson strip before it can build there.
The bridge's supporters and opponents agree on where it goes. They disagree about what it would do once traffic is using it.
The city's case is about access, a second way in and out of the south end of town. The Garfield County commissioner race this fall showed how broadly that idea is accepted. As the Post Independent reported from a September candidate forum, Jonathan Godes and Eric Rudd both supported South Bridge. They split on the county's lawsuit. Godes opposed it, and Aspen Public Radio reported his concern about delay and funding risk. Rudd backed the commissioners' decision and pointed to the project's price.
Opponents focus on what the bridge would bring onto the city's own streets. In an August 28 letter in the Aspen Daily News, a Glenwood Springs resident argued the bridge would not fix the town's traffic. He estimated it could send about 3,000 cars twice a day onto Midland Avenue. In a September 1 letter to the Post Independent, Sandy Jackson wrote that the ranch has been in her family since 1955. She called for a current valleywide environmental review and for the county's 1041 review.
Both views affect a south Glenwood address, in different ways. A home near the Four Mile roundabout or along South Midland could gain a shorter route to Highway 82. It could also end up on the street that carries the new traffic. Which outcome a given block gets depends on how the bridge is finally designed, permitted and built, and none of that has been decided.
When a listing description, a neighbor or an online forum says a second bridge is coming, it is describing a project with an unresolved county lawsuit, a need for county permits and land the city doesn't yet have. The timeline has already slipped once.
The same applies to protected open space. On the Jackson Ranch, a conservation easement is now the subject of a condemnation authorization. If part of the appeal of a property is undeveloped land next door, it helps to know who holds that land's protections and whether any public project's route crosses it.
A few questions are worth putting to the public record before you make an offer in this part of town:
This post is general information about a public project, not legal or financial advice. Questions about eminent domain, easements or land-use review for a specific property belong with a qualified attorney.
The South Bridge timeline will keep changing, and how it affects a south Glenwood home depends on the block. If you're weighing a property near Airport Road or South Midland and want help reading where the project stands on the day you write your offer, Theo Williams can walk you through the latest city and county record. Start Your Aspen Search, and we'll start with the bridge.